Echo Agronomy – Phase 2
November 4, 2026 – Finishing up the shop’s interior steel & the seed shed’s exterior
Geihl Construction has been hard at work erecting both our new shop and seed shed. They are just finishing up installing the interior steel on the shop and are wrapping up the exterior of the seed shed. They have poured the slab for the bulk seed bins to be placed on and have installed the dock leveler to receive seed shipments. Our own crews have been working on their parts of the projects as well – the LP department was here yesterday installing the heaters for the shop, and the electricians are going to be working on lighting and finishing up the wiring. Just waiting on the doors to be installed and we will be that much closer to being in business.



August 11, 2026 – Starting on shop interior & waiting on steel for seed shed
The new company shop has been insulated, and we are installing the floor drains so we can pour concrete this week. After that is completed, the septic will get hooked up and then we’ll be able to start on the electrical work inside. We are still waiting on steel to be delivered for the seed shed.



June 1, 2026 – Foundations are complete
The foundations are complete for the seed warehouse and shop. We’re looking forward to getting the floors poured and erecting the steel structures!



May 1, 2026 – Preparing for concrete
The second phase of the Echo Agronomy Center Complex continues this spring! As originally planned, a seed warehouse and company shop are being constructed this year. Both buildings are Sukup steel buildings. Currently, the site is being prepared for concrete work.



